Welcome to your Electrical Vehicle Charging exam simulator
1.
Which one of the following is a statutory document?
2.
If the installer of a Domestic EV Car charging point is not registered with a Competent Person Scheme, what are they required to do if the installation is not listed or in a conservation area?
3.
What is a Type 2 Connector also known as?
4.
Which one of the following is a likely hazard if charging equipment is located too far from the vehicle inlet?
5.
An existing electrical installation forms part of a TNS earthing arrangement. Which one of the following statements is true regarding the earthing arrangement charging equipment to be installed?
6.
How often shall the client be advised to test the RCD by pressing the test button?
7.
Electric vehicle charging equipment must be?
8.
Which one of the following describes mode 1 charging?
9.
Charging equipment that is to be installed in an outdoor location shall have an IP rating of at least?
10.
Which of the following should the installation of electrical vehicle charging equipment comply with?
11.
Which one of the following diversity ratings should be applied to charging equipment without any automatic limit controls?
12.
What type of connector is shown?
13.
Which one of the following is contained on a DNO notification form?
14.
Which one of the following organisations should be consulted prior to the installation of electric vehicle charging equipment in a domestic property, by an installer who is not registered on a self-assessment scheme?
15.
If the installation is to incorporate Island mode capability, which approval notification should be used?
16.
What type of connector is shown?
17.
Which one of the following descriptions relating to the extent of an Electrical Installation Certificate would be ticked if charging equipment was installed using a dedicated new circuit?
18.
Which one of the following details relating to the supply must be given on an Electrical Installation Certificate?
20.
Which one of the following describes mode 4 charging?
21.
If the electric vehicle charging equipment is to be installed in a guaranteed TN-S system which one of the following is true?
22.
In the event of an open-circuit fault to the PEN conductor of a TNCS PME system?
23.
A client who lives on the upper floor of a high rise residential block requires charging equipment to be installed in a basement garage area. Which one of the following should permission be sought from?
24.
What do the letters CLA stand for when considering a Vehicle being used as electricity storage?
25.
Using the tables in Annex F, If the If the maximum demand including the charging equipment was at 60Amps. What would be the maximum value of RAev?
26.
When using a vehicle as storage what is the recommended volt drop between invertor and point of contact to the grid?
27.
Which test procedure would verify the CPC is correctly selected and installed on an EVSE circuit?
28.
Which one of the following is required to verify, by inspection, that Automatic Disconnection of supply is suitable?